A) $28,939
B) $30,462
C) $32,066
D) $33,753
E) $35,530
Correct Answer
verified
Multiple Choice
A) $23,852
B) $25,045
C) $26,297
D) $27,612
E) $28,993
Correct Answer
verified
Multiple Choice
A) Only incremental cash flows, which are the cash flows that would result if a project is accepted, are relevant when making accept/reject decisions.
B) Sunk costs are not included in the annual cash flows, but they must be deducted from the PV of the project's other costs when reaching the accept/reject decision.
C) A proposed project's estimated net income as determined by the firm's accountants, using generally accepted accounting principles (GAAP) , is discounted at the WACC, and if the PV of this income stream exceeds the project's cost, the project should be accepted.
D) If a product is competitive with some of the firm's other products, this fact should be incorporated into the estimate of the relevant cash flows. However, if the new product is complementary to some of the firm's other products, this fact need not be reflected in the analysis.
E) The interest paid on funds borrowed to finance a project must be included in estimates of the project's cash flows.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) All sunk costs that have been incurred relating to the project.
B) All interest expenses on debt used to help finance the project.
C) The investment in working capital required to operate the project, even if that investment will be recovered at the end of the project's life.
D) Sunk costs that have been incurred relating to the project, but only if those costs were incurred prior to the current year.
E) Effects of the project on other divisions of the firm, but only if those effects lower the project's own direct cash flows.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Increase the estimated NPV of the project to reflect its greater risk.
B) Reject the project, since its acceptance would increase the firm's risk.
C) Ignore the risk differential if the project would amount to only a small fraction of the firm's total assets.
D) Increase the cost of capital used to evaluate the project to reflect its higher-than-average risk.
E) Increase the estimated IRR of the project to reflect its greater risk.
Correct Answer
verified
Multiple Choice
A) Differential project risk cannot be accounted for by using "risk-adjusted discount rates" because it is highly subjective and difficult to justify. It is better to not risk adjust at all.
B) Other things held constant, if returns on a project are thought to be positively correlated with the returns on other firms in the economy, then the project's NPV will be found using a lower discount rate than would be appropriate if the project's returns were negatively correlated.
C) Monte Carlo simulation uses a computer to generate random sets of inputs, those inputs are then used to determine a trial NPV, and a number of trial NPVs are averaged to find the project's expected NPV. Sensitivity and scenario analyses, on the other hand, require much more information regarding the input variables, including probability distributions and correlations among those variables. This makes it easier to implement a simulation analysis than a scenario or a sensitivity analysis, hence simulation is the most frequently used procedure.
D) DCF techniques were originally developed to value passive investments (stocks and bonds) . However, capital budgeting projects are not passive investments⎯managers can often take positive actions after the investment has been made that alter the cash flow stream. Opportunities for such actions are called real options. Real options are valuable, but this value is not captured by conventional NPV analysis. Therefore, a project's real options must be considered separately.
E) The firm's corporate, or overall, WACC is used to discount all project cash flows to find the projects' NPVs. Then, depending on how risky different projects are judged to be, the calculated NPVs are scaled up or down to adjust for differential risk.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A and B.
B) A, B, and C.
C) A, B, and D.
D) A, B, C, and D.
E) A, B, C, D, and E.
Correct Answer
verified
Multiple Choice
A) In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project's cash flows will lead to a downward bias in the NPV.
B) The existence of any type of "externality" will reduce the calculated NPV versus the NPV that would exist without the externality.
C) If one of the assets to be used by a potential project is already owned by the firm, and if that asset could be sold or leased to another firm if the new project were not undertaken, then the net after-tax proceeds that could be obtained should be charged as a cost to the project under consideration.
D) If one of the assets to be used by a potential project is already owned by the firm but is not being used, then any costs associated with that asset is a sunk cost and should be ignored.
E) In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project's cash flows will lead to an upward bias in the NPV.
Correct Answer
verified
Multiple Choice
A) Sunk costs must be considered if the IRR method is used but not if the firm relies on the NPV method.
B) A good example of a sunk cost is a situation where a bank opens a new office, and that new office leads to a decline in deposits of the bank's other offices.
C) A good example of a sunk cost is money that a banking corporation spent last year to investigate the site for a new office, then expensed that cost for tax purposes, and now is deciding whether to go forward with the project.
D) If sunk costs are considered and reflected in a project's cash flows, then the project's calculated NPV will be higher than it otherwise would be.
E) An example of a sunk cost is the cost associated with restoring the site of a strip mine once the ore has been depleted.
Correct Answer
verified
Multiple Choice
A) $13,286
B) $13,985
C) $14,721
D) $15,457
E) $16,230
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) One advantage of sensitivity analysis relative to scenario analysis is that it explicitly takes into account the probability of specific effects occurring, whereas scenario analysis cannot account for probabilities.
B) Well-diversified stockholders do not need to consider market risk when determining required rates of return.
C) Market risk is important, but it does not have a direct effect on stock prices because it only affects beta.
D) Simulation analysis is a computerized version of scenario analysis where input variables are selected randomly on the basis of their probability distributions.
E) Sensitivity analysis is a good way to measure market risk because it explicitly takes into account diversification effects.
Correct Answer
verified
Multiple Choice
A) An example of an externality is a situation where a bank opens a new office, and that new office causes deposits in the bank's other offices to decline.
B) The NPV method automatically deals correctly with externalities, even if the externalities are not specifically identified, but the IRR method does not. This is another reason to favor the NPV.
C) Both the NPV and IRR methods deal correctly with externalities, even if the externalities are not specifically identified. However, the payback method does not.
D) Identifying an externality can never lead to an increase in the calculated NPV.
E) An externality is a situation where a project would have an adverse effect on some other part of the firm's overall operations. If the project would have a favorable effect on other operations, then this is not an externality.
Correct Answer
verified
Showing 21 - 40 of 78
Related Exams