Figure Figure   (time in days)  -What is the estimated standard deviation in the time for activity E? A) 1 days. B) 2 days. C) 3 days. D) 4 days. E) 5 days. (time in days) -What is the estimated standard deviation in the time for activity E?


A) 1 days.
B) 2 days.
C) 3 days.
D) 4 days.
E) 5 days.

F) A) and E)
G) All of the above

Correct Answer

verifed

verified

B

Figure Figure   (time in days)  -What is the probability that the critical path will be completed within 200 days? A) 0.8413. B) 0.9544. C) 0.9772. D) 0.9974. E) 0.9987. (time in days) -What is the probability that the critical path will be completed within 200 days?


A) 0.8413.
B) 0.9544.
C) 0.9772.
D) 0.9974.
E) 0.9987.

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

The earliest start of an activity is the latest early finish of any immediately preceding activity.

A) True
B) False

Correct Answer

verifed

verified

Figure Figure   -The path with the greatest slack is: A) A-E. B) B-F. C) C-D-F. D) C-G. E) None of the above. -The path with the greatest slack is:


A) A-E.
B) B-F.
C) C-D-F.
D) C-G.
E) None of the above.

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

PERT/Cost can be used to monitor budget overruns.

A) True
B) False

Correct Answer

verifed

verified

The project network diagram describes sequential relationships among major activities in a project.

A) True
B) False

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated mean time for project completion? A) 100 days. B) 140 days. C) 199 days. D) 200 days. E) 440 days. (time in days) -What is the estimated mean time for project completion?


A) 100 days.
B) 140 days.
C) 199 days.
D) 200 days.
E) 440 days.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

When using linear programming to make crashing decisions,the objective is to minimize:


A) the total cost of crashing the project.
B) the total of the durations of the activities on the critical path.
C) the latest finish time of the finish node.
D) the total number of activities on the critical path.
E) None of the above.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

The slack of an activity is the difference between the latest finish and the earliest finish times.

A) True
B) False

Correct Answer

verifed

verified

The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities.

A) True
B) False

Correct Answer

verifed

verified

True

The standard deviation of a path is computed as:


A) the sum of the standard deviations of all activities on the path.
B) the square root of the sum of the standard deviations of all activities on the path.
C) the sum of the variances of all activities on the path.
D) the square root of the sum of the variances of all activities on the path.
E) None of the above.

F) A) and D)
G) B) and D)

Correct Answer

verifed

verified

PERT/Cost is a systematic procedure to help a project manager bid on a project.

A) True
B) False

Correct Answer

verifed

verified

  Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23? A) 3. B) 4. C) 9. D) 10. E) 12. Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?


A) 3.
B) 4.
C) 9.
D) 10.
E) 12.

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity.

A) True
B) False

Correct Answer

verifed

verified

The activities with the longest durations in a project network are called critical activities.

A) True
B) False

Correct Answer

verifed

verified

The earliest start time for an activity is:


A) based on the length of the critical path.
B) determined by the maximum of the earliest finish times of its immediate predecessors.
C) determined by the maximum of the earliest finish times of its immediate successors.
D) the same as the latest start time of its immediate predecessor.
E) None of the above.

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

In PERT,the project duration will never exceed the expected duration of the critical path.

A) True
B) False

Correct Answer

verifed

verified

False

The project management strategy of injecting additional resources in order to reduce the length of the project is called:


A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) None of the above.

F) A) and E)
G) C) and E)

Correct Answer

verifed

verified

At which point does crashing of a project cease?


A) When the project is completed.
B) When no additional crashing is possible.
C) When the cost to crash equals or exceeds the benefit of crashing.
D) All of the above.
E) None of the above.

F) D) and E)
G) All of the above

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated mean time for project completion? A) 160 days. B) 170 days. C) 200 days. D) 210 days. E) 300 days. (time in days) -What is the estimated mean time for project completion?


A) 160 days.
B) 170 days.
C) 200 days.
D) 210 days.
E) 300 days.

F) B) and C)
G) All of the above

Correct Answer

verifed

verified