A) The NPV, IRR, MIRR, and discounted payback (using a payback requirement of 3 years or less) methods always lead to the same accept/reject decisions for independent projects.
B) For mutually exclusive projects with normal cash flows, the NPV and MIRR methods can never conflict, but their results could conflict with the discounted payback and the regular IRR methods.
C) Multiple IRRs can exist, but not multiple MIRRs. This is one reason some people favor the MIRR over the regular IRR.
D) If a firm uses the discounted payback method with a required payback of 4 years, then it will accept more projects than if it used a regular payback of 4 years.
E) The percentage difference between the MIRR and the IRR is equal to the project's WACC.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) For a project to have more than one IRR, then both IRRs must be greater than the WACC.
B) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
C) If a project is independent, then it cannot have multiple IRRs.
D) Multiple IRRs can only occur if the signs of the cash flows change more than once.
E) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If a project's IRR is equal to its WACC, then, under all reasonable conditions, the project's NPV must be negative.
B) If a project's IRR is equal to its WACC, then under all reasonable conditions, the project's IRR must be negative.
C) If a project's IRR is equal to its WACC, then under all reasonable conditions the project's NPV must be zero.
D) There is no necessary relationship between a project's IRR, its WACC, and its NPV.
E) When evaluating mutually exclusive projects, those projects with relatively long lives will tend to have relatively high NPVs when the cost of capital is relatively high.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
C) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
D) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
E) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
Correct Answer
verified
Multiple Choice
A) Each project must have a negative NPV.
B) Since the projects are mutually exclusive, the firm should always select Project B.
C) If the crossover rate is 8%, Project B will have the higher NPV.
D) Only one project has a positive NPV.
E) If the crossover rate is 8%, Project A will have the higher NPV.
Correct Answer
verified
Multiple Choice
A) Project D probably has a higher IRR.
B) Project D is probably larger in scale than Project C.
C) Project C probably has a faster payback.
D) Project C probably has a higher IRR.
E) The crossover rate between the two projects is below 12%.
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
B) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
C) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
D) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
E) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
Correct Answer
verified
Multiple Choice
A) Project S.
B) Project L.
C) Both projects are equally sensitive to changes in the WACC since their NPVs are equal at all costs of capital.
D) Neither project is sensitive to changes in the discount rate, since both have NPV profiles that are horizontal.
E) The solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative IRRs.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) For a project with normal cash flows, any change in the WACC will change both the NPV and the IRR.
B) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV.
C) The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
E) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 72
Related Exams